Shaanxi Meixin's 300,000tpy Al-Mg power substation project passes inspection
2018-05-30 17:35:53 [Print]
On May 25, 2018, a 12-member expert team from State Grid Shaanxi Electric Power Company and Tongchuan City Power Supply Bureau conducted inspection on the 300,000tpy Al-Mg power substation project constructed by Shaanxi Meixin Industry Investment Co
The inspection team thought highly of construction quality of the project but also pointed out things to be improved. The company leaders promised to complete relevant rectification work as soon as possible to guarantee that the substation facilities go into operation smoothly and safely.
. , Ltd . The team was first briefed by the company staff on construction information of the project, and then conducted thorough inspection on substation units, rectifier cabinets, 330KV switching units and controlling cabinet of main controlling building, and also reviewed related engineering documents. The inspection team thought highly of construction quality of the project but also pointed out things to be improved. The company leaders promised to complete relevant rectification work as soon as possible to guarantee that the substation facilities go into operation smoothly and safely.